AN Police · Numerical Aptitude

More Andaman and Nicobar Islands government exams →

Time and Work

Pipes, cisterns and combined work problems.

Test yourself on Time and Work

5 practice questions for AN Police with instant answers — no signup, ~3 minutes.

Take the 5-question quiz →

Study notes are still being prepared.

Don't wait — Shishya can teach you this topic right now, on demand.

Ask Shishya to teach this →

Need more? Ask Shishya

Shishya is your personal tutor for this topic. Pick a starter or open a free chat.

Open Shishya tutor →

Practice this topic

Take a full mock →
  • Q1 · Time and Work · MEDIUM

    A can complete a work in 12 days and B can complete the same work in 18 days. If they work together, in how many days will they complete the work?

  • Q2 · Time and Work · MEDIUM

    A can complete a work in 12 days and B can complete the same work in 18 days. In how many days will they complete the work together?

  • Q3 · Time and Work · MEDIUM

    If 8 workers can complete a task in 12 days, how many days will 6 workers take to complete the same task?

  • Q4 · Time and Work · MEDIUM

    A can complete a work in 15 days and B can complete the same work in 20 days. If they work together, in how many days will the work be completed?

  • Q5 · Time and Work · MEDIUM

    A can complete a work in 12 days and B can complete the same work in 18 days. If they work together, in how many days will they complete the work?

Ask Shishya to explain these →