Certificates / Quantitative aptitude / Time and Work

Time and Work: lesson, then the certificate test

Step 1: the lesson (about 1 min)

Think in work per day: someone who finishes a job in n days does 1/n of it each day.

  • Working together, ADD the per-day work, never the days.
  • Easy trick: take the total work as the LCM of the days, then work out each person's units per day.
  • Days needed = total work ÷ work per day.

Worked example

A can finish a job in 12 days and B in 15 days. How long do they take together?

  • Total work = LCM(12, 15) = 60 units
  • A does 5 units a day, B does 4 units a day: 9 units a day together
  • 60 ÷ 9 = 6⅔ days

Answer: 6⅔ days

Watch out

  • Adding the days (12 + 15) or averaging them is always wrong.

Made by Shishya (AI-assisted): a general method in our own words, with our own example; no exam or platform question is copied.