More West Bengal government exams →
Time and Work
Work Efficiency, Pipes and Cisterns, Work and Wages
Test yourself on Time and Work
Practice questions for WBCS on this topic with instant answers — no signup.
Study notes are still being prepared.
Don't wait — Shishya can teach you this topic right now, on demand.
Ask Shishya to teach this →Need more? Ask Shishya
Shishya is your personal tutor for this topic. Pick a starter or open a free chat.
- Go deeper on this topicGo deeper on Time and Work for WBCS — examples and edge cases I should know.
- Show me exam shortcutsGive me 3 fastest shortcuts to solve Time and Work questions in the exam.
- What mistakes should I avoid?What are the most common mistakes students make on Time and Work? How do I avoid them?
- Quiz me adaptivelyQuiz me on Time and Work — start with one easy question, then go harder based on how I answer.
Practice this topic
Take a full mock →Q1 · Time and Work · MEDIUM
Three workers A, B, and C can complete a task in 15 days, 20 days, and 30 days respectively. If all three start working together, but A leaves 5 days before the work is completed, in how many days will the work be finished?
Q2 · Time and Work · EASY
If 8 men can complete a work in 12 days, how many days will 6 men take to complete the same work?
Q3 · Time and Work · MEDIUM
Rajiv can complete a task in 18 days while Sunil can complete the same task in 27 days. They work together for 6 days and then Rajiv leaves. In how many more days will Sunil finish the remaining work?
Q4 · Time and Work Basics · HARD
A can complete a work in 12 days and B can complete the same work in 18 days. If they work together, in how many days will they complete the work?