KPSC Group C · Quantitative Aptitude
More Karnataka government exams →
Time and Work
Work efficiency, pipes and cisterns.
Test yourself on Time and Work
Practice questions for KPSC Group C on this topic with instant answers — the first 2 free, then sign up free with Google.
Study notes are still being prepared.
Don't wait — Shishya can teach you this topic right now, on demand.
Ask Shishya to teach this →About this topic in KPSC Group C
- Practice: 4 answer-checked practice questions on Time and Work for KPSC Group C — practise them.
- Next exam day: KEA FDA/SDA graduate and PUC-level exams (expected, tentative): 9 Jan 2027 (Expected — an estimate, not announced).
Signed-in students aged 13 and above can share their own notes on Time and Work here; a moderator reads each one first.
Need more? Ask Shishya
Shishya is your personal tutor for this topic. Pick a starter or open a free chat.
- Go deeper on this topicGo deeper on Time and Work for KPSC Group C — examples and edge cases I should know.
- Show me exam shortcutsGive me 3 fastest shortcuts to solve Time and Work questions in the exam.
- What mistakes should I avoid?What are the most common mistakes students make on Time and Work? How do I avoid them?
- Quiz me adaptivelyQuiz me on Time and Work — start with one easy question, then go harder based on how I answer.
Practice this topic
Take a full mock →Q1 · Time and Work · EASY
A and B together can complete a work in 12 days. A alone can complete it in 20 days. How many days will B alone take to complete the work?
Q2 · Time and Work · HARD
A cistern can be filled by two pipes A and B in 8 hours and 12 hours respectively. Pipe C can empty the full cistern in 6 hours. If all three pipes are opened simultaneously, in how many hours will the cistern be filled?
Q3 · Time and Work · EASY
A and B together can complete a piece of work in 15 days. A alone can complete the same work in 20 days. In how many days can B alone complete the work?
Q4 · Time and Work · HARD
12 men can complete a task in 18 days. After 6 days, 4 men left the work. In how many more days will the remaining men complete the task?