MH Police Bharti · Mathematics

More Maharashtra government exams →

Time & Work

Work, wages, pipes and cisterns.

Share with your prep group:WhatsApp

Test yourself on Time & Work

Practice questions for MH Police Bharti on this topic with instant answers — no signup.

Take the quick quiz →

Time & Work

Overview

Time & Work is a high-scoring topic in Maharashtra Police Bharti Mathematics. Questions test your ability to calculate how long workers take to complete jobs, how wages should be distributed, and how pipes fill or empty tanks.

The core idea is simple: work is measured as a fraction of the total job. If a person completes a task in 10 days, they do 1/10 of the work each day. Master this concept and you can solve most problems mentally. The topic connects directly to Ratio & Proportion — wages are distributed in the ratio of work done, and combined work rates add up like fractions.

Focus areas for the exam: basic work-rate problems, two or three workers combining, workers leaving mid-way, wages distribution, and pipes & cisterns with filling and emptying pipes working together.

Key Concepts

  • Work Rate: If A completes work in n days, A's one day work = 1/n. This is the fundamental building block.
  • Combined Work: When A and B work together, their combined one day work = 1/a + 1/b, where a and b are their individual completion times.
  • LCM Method: Assume total work = LCM of individual times. This converts fractions to whole numbers, making calculations faster.
  • Inverse Relationship: More workers means less time (if efficiency is same). Time is inversely proportional to number of workers.
  • Work = Rate × Time: Just like Distance = Speed × Time. This formula governs all variations.
  • Wages Ratio = Work Ratio: If A does 3 units and B does 2 units, wages split in 3:2 ratio, regardless of time spent.
  • Pipes & Cisterns: Filling pipe has positive rate, emptying pipe (leak) has negative rate. Net rate = sum of all rates.
  • Efficiency Ratio: If A is twice as efficient as B, then A's rate = 2 × B's rate, so A takes half the time.

Formulas / Key Facts

SituationFormula
A's one day work1/A (where A = days to complete)
A and B togetherTime = (A × B)/(A + B) days
A, B, C togetherTime = 1/(1/A + 1/B + 1/C) days
Work doneW = Rate × Time
Remaining work1 − (work already done)
Wages distributionRatio of wages = Ratio of work done
Pipe filling tankTime = Tank capacity / Fill rate
Pipe emptying tankTime = Tank capacity / Empty rate
Net rate (fill + leak)1/Fill time − 1/Empty time
Man-days conceptM₁ × D₁ = M₂ × D₂ (for same work)

Quick fact: When a filling pipe and leak work together, if filling time = F and emptying time = E, net time to fill = (F × E)/(E − F), valid only when E > F.

Worked Examples

Example 1: Basic Combined Work

Problem: A can do a work in 12 days, B can do it in 18 days. In how many days will they finish working together?

Solution:

  • A's one day work = 1/12
  • B's one day work = 1/18
  • Combined one day work = 1/12 + 1/18 = 3/36 + 2/36 = 5/36
  • Time to complete = 36/5 = 7.2 days or 7 days 4 hours

Using formula: (12 × 18)/(12 + 18) = 216/30 = 7.2 days ✓


Example 2: Worker Leaves Mid-Way

Problem: A and B can complete work in 12 days. A alone can do it in 20 days. After working together for 4 days, A leaves. How many more days will B take to finish?

Solution:

  • Combined one day work = 1/12
  • Work done in 4 days = 4 × 1/12 = 1/3
  • Remaining work = 1 − 1/3 = 2/3
  • A's one day work = 1/20
  • B's one day work = 1/12 − 1/20 = (5 − 3)/60 = 2/60 = 1/30
  • Time for B to finish 2/3 work = (2/3) ÷ (1/30) = (2/3) × 30 = 20 days

Example 3: Pipes & Cisterns

Problem: Pipe A fills a tank in 6 hours. Pipe B empties it in 8 hours. If both are opened, how long to fill the tank?

Solution:

  • A's rate = +1/6 per hour (filling)
  • B's rate = −1/8 per hour (emptying)
  • Net rate = 1/6 − 1/8 = 4/24 − 3/24 = 1/24 per hour
  • Time to fill = 24 hours

Example 4: Wages Distribution

Problem: A can do work in 6 days, B in 8 days. They work together and get ₹2800. Find A's share.

Solution (LCM Method):

  • Total work = LCM(6, 8) = 24 units
  • A's daily work = 24/6 = 4 units
  • B's daily work = 24/8 = 3 units
  • Work ratio = 4:3
  • A's share = (4/7) × 2800 = ₹1600

Common Mistakes

  • Adding times instead of rates: Wrong: "A takes 10 days, B takes 15 days, together = 25 days." Fix: Add work rates (1/10 + 1/15), not times.
  • Forgetting negative sign for leaks: Wrong: Adding leak rate as positive. Fix: Emptying pipes always subtract from filling rate.
  • Confusing work done vs work remaining: Wrong: Calculating time for total work after partial completion. Fix: Always find remaining work first, then apply rates.
  • Equal wages for equal time: Wrong: Assuming same hours worked = same wages. Fix: Wages depend on work done, not time. Faster worker earns more per day.
  • Wrong LCM application: Wrong: Using LCM as answer directly. Fix: LCM is assumed total work; still need to calculate combined rate and divide.
  • Ignoring efficiency differences: Wrong: Treating "A is twice as efficient" as A takes twice the time. Fix: Twice efficient means half the time.

Quick Reference

  • A alone in n days → One day work = 1/n
  • A + B together → Time = (A × B)/(A + B)
  • LCM method: Total work = LCM, then work per day = LCM ÷ individual time
  • Wages ratio = Work done ratio (not time ratio)
  • Pipes: Fill rate positive, Leak rate negative, Net rate = sum
  • Man-days constant: M₁D₁ = M₂D₂ for same work

Drafted with AI from Shishya's syllabus outline for this exam · Reviewed by a person: not yet · Report an error

You read the notes — now try one

A can complete a work in 12 days and B can complete the same work in 18 days. If both work together, in how many days will they complete the work?

Tap an option to check your answer.

👥 Study this together

Invite your prep group — read the same notes, then discuss doubts in this topic's shared room.

Invite to study

Need more? Ask Shishya

Shishya is your personal tutor for this topic. Pick a starter or open a free chat.

Open Shishya tutor →

Practice this topic

Take a full mock →
  • Q1 · Time & Work · EASY

    A can complete a work in 12 days and B can complete the same work in 18 days. If both work together, in how many days will they complete the work?

  • Q2 · Time & Work · MEDIUM

    15 workers can complete a construction work in 20 days. After 10 days of work, 5 more workers joined. In how many more days will the work be completed?

  • Q3 · Time & Work · MEDIUM

    A pipe can fill a tank in 6 hours. Another pipe can empty the full tank in 9 hours. If both pipes are opened together in the empty tank, in how many hours will the tank be filled?

Ask Shishya to explain these →

Notes generated on 11 Sept 2026